This note is a practical guide to the law relating to party walls. It also explains the consequences of failing to follow the correct procedures.

What is a party wall?

A party wall is a wall that stands on a boundary between a building owner’s land and the land of an adjoining owner. As well as walls that divide buildings, party structures can also include garden walls and horizontal floors or ceilings between flats.

Giving notice of works to party walls

The building owner must give notice to all adjoining owners of any planned works. The notice requirements will depend on the type of work that is being done. Adjoining owners may serve counter-notices in some situations.

Procedure for carrying out works

The procedure is set out in the table below.

  Existing walls New walls Excavation
Notice required 2 months 1 month 1 month
Counter-notice Within 1 month N/A Within 14 days
Content of counter-notice Adjoining owner requires additional works N/A Adjoining owner requires foundations strengthened
If in agreement Carry out works Build wall on boundary Begin excavation
If in dispute Refer to surveyors Build the wall on the building owner’s land or refer to surveyors Refer to surveyors
Security for expenses Adjoining owner must serve notice on the building owner if security is required
Appoint party wall surveyors Parties elect to appoint an agreed party wall surveyor (or separate surveyors who then agree on the appointment of a third surveyor)
A party wall award provides: The right to execute works; details of the timing and manner of the works; who is liable for the costs and expenses of the award and in what proportion; and the amount of any security for expenses
Appeal Either party may appeal to the court within 14 days of the service of the award
Written consent Written consent is always needed for sinking special foundations on the adjoining owner’s land
Right of entry 14 days’ notice should be given by the building owner to the adjoining owner (except in emergencies)
Execution of the works Start works within 12 months of the date of the notice
Serve an account The building owner must serve an account within 2 months of the completion of the works if the adjoining owner is partially liable for the expenses
Payments The property remains vested in the building owner until the adjoining owner settles its share of the expenses

 Consequences of failing to follow the correct procedures

Failure to serve a notice

A building owner will be in breach of the statutory procedure if they fail to serve a notice at all; fail to serve the correct notice, or serve a notice on the wrong recipient.

In most cases a failure to serve notice can be resolved by the building owner stopping the work and following the correct procedures. However, if a building owner persistently refuses to follow the correct procedure the adjoining owner may seek an injunction prohibiting them from continuing the work. In some instances an injunction will not be appropriate (for example, where the building owner’s works have been completed). The adjoining owner may then bring court proceedings against the building owner and seek compensation.

Failure to appoint a surveyor

If one party will not consent to the appointment of an agreed party wall surveyor and fails to appoint a surveyor of their own then the other party can make an appointment on their behalf.

Refusal to give access

If a person is entitled to carry out work and has given 14 days’ notice of proposed entry it is an offence for an adjoining owner to refuse access to land or to obstruct a person from carrying out work. A building owner and his agents may (with police assistance) break open any fences or doors that prevent the building owner from exercising his right of access to adjoining land to carry out works.

Building owner goes beyond the remit of the party wall surveyor’s decision

If a building owner goes beyond the remit of the party wall surveyor’s decision and causes loss or damage by carrying out works they may be sued for damages.

Contact us

If you have any questions about the law relating to party walls, please contact:

Further reading

DMH Stallard advises Optiva Securities as broker to Asiamet Resources in £10 million equity fundraising

News & PR
05/03/2021
Nick Williams advised Optiva Securities Limited on its role as broker in arranging a successful firm placing and accelerated bookbuild placing for Asiamet Resources Limited.
Read more Read

DMH Stallard advises Whyte Bikes on private equity investment

Blog, News & PR
05/03/2021
Helen Mead led the team advising innovative bicycle manufacturer on investment
Read more Read

SDLT: the holiday the housing sector would like to extend

Blog, Legal Updates
03/03/2021
Raising the SDLT threshold in 2020 kept the housing market booming; Rachel Munroe considers what developers would like to see in 2021
Read more Read

The Supreme Court & Vicarious Liability: The Importance of Worker Status

Blog
03/03/2021
HR Professionals have primarily been concerned with Covid-19 and its impact on their businesses, but there have been other significant developments in employment law relating to vicarious liability.
Read more Read
  • Brighton Office

    1 Jubilee Street

    Brighton

    East Sussex

    BN1 1GE

  • Gatwick Office

    Griffin House

    135 High Street

    Crawley

    West Sussex

    RH10 1DQ

  • Guildford Office

    Wonersh House

    The Guildway

    Old Portsmouth Road

    Guildford

    Surrey

    GU3 1LR

  • Horsham Office

    Ridgeland House

    15 Carfax

    Horsham

    West Sussex

    RH12 1DY

  • London Office

    6 New Street Square

    New Fetter Lane

    London

    EC4A 3BF

  • Get in touch